Howden Recreation Centre

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

​​

Reviewed: 10/​28​​​​/2024


Gallery

Construction of a new Howden Recreation Centre is anticipated after the demolition of the existing structure has been completed. The new facility will include a multipurpose gymnasium with a FIBA-sized court, several multipurpose rooms, outdoor courts and play areas. 

Project highlights:
  • ​Estimated Building size 45,000 sq.ft
  • LEED gold and Net Zero Ready Status
  • Indoor facilities include a multi-sport gymnasium, change rooms, and multipurpose rooms for meetings and events
  • Outdoor facilities include multisport courts, leased spaces for a day care centre, and outdoor play areas
  • Landscape of entire site in addition to parking and other outdoor amenities​​​​

  • Q3 2021: Demolition complete 
  • Q4 2021: Soccer field construction substantially complete ​
  • Q3 2024: Design complete 
  • Q4 2024 Tender award target
  • Q4 2024: Construction start 
  • Q4​​ 2026: Estimated project completion​​

​Site Location:

150 Howden Blvd.

​​